Saturday, April 19, 2008

Chapter 9 - Landing brake - Part 3

Over the last week I have been making some slow progress on the landing brake. I have quite a bit of work left on this brake, from faring to the control hardware ( I am seriously considering an electric actuator over the lever, cables, springs etc..). What follows are some photos of the process since my last landing break post....

Here are three plies BID layed up over the foam core of the landing brake. Note the duct tape to prevent the landing brake plies from bonding to the fuse.



Here is the brake after the outside skin has cured. You can see the foam core, aluminum piano hinge and plywood reinforcement (later to cause some difficulty).


Here is the brake following lay up and cure of the inside 3 plied of BID. The piano hinge is bolted to the fuse through three holes drilled and tapped into the aluminum blocks installed previously.


The landing brake in the open position.


Here is a close up shot of the hinge. I had to remove a portion of the plywood block because it was interfering with the center bolt and would not allow the brake to fully close. I will lay up 3 to 6 plys BID in place of the plywood block in that area. I have AN screws that will be placed in the remaining 4 holes, but I will need washers for those.

Friday, April 11, 2008

Chapter 9 - Main wheels

Not much to say here, but WHEELS!

Pictured below are a pair of Matco W51LT wheels.
I went through some different options in my head for the wheels and finally decided to go with th matcos. They provide sufficient braking power and are available at the right price. These were purchaed as a kit from Wicks and include wheel, break bearings, axles axle nut etc...

Sunday, April 6, 2008

Chapter 9 - Landing brake - Part 2

I did more work on the landing brake today. Here I have 5 min. epoxied the 3 LB22 aluminum blocks to the "front" of LB23 (1/4" spruce plywood). These aluminum blocks will later be drilled out and tapped to receive bolts to attach to the piano hinge for the landing brake.



Test fitting LB 23 with aluminum blocks attached with epoxy. This piece is later micro'd in place.


Landing brake recess ready for glassing


Landign brake resess after glassing.




Saturday, April 5, 2008

Chapter 8/9 - Seat belts, main gear, and landing brake.

Ok, I have quite a bit going on at once now. The seat belts arrived from ACS. Pictured is the front belts test fitted.



Here is the step that I fabricated. After all the cutting drilling bending hammering etc. I should have just bought one premade from the cozy girrrl. I probably would not have saved any money and I would have save quite a bit of time. Lessons learned. I still need to do some additional bending and counter sink the two inner holes.


The main landing gear her is pictured after I laid up the first 4 torsional plies of UNI. I have since finnished all 8 and I am working on the break line conduit. More on that later.



The final two pictures show the first couple of steps involved in fabricating and installing the landing break.


The use of my brothers Fein tool made removal of the fiberglass skin here a painless process. Now I have a little bit of foam shaping to do. More blue dust to come!!

Saturday, March 15, 2008

Chapter 7 - Seat belts and rollover - Part 3

Pictured below is one of the four seat belt reenforcement first is a 1/4 plywood block followed by 7 layers of BID fiberglass. The remaining parts for this chapter are on the way (except the seat belts). Only about an hour left on this chapter and on to the main landing gear prep and installation.


Monday, March 10, 2008

Chapter 7 - Seat belts and rollover - Part 2

This weekend I assembled the headrest. After glassing I cut out map hole and the round hole at the back of the headrest. After searching all over my shop the only round thing I could find that matched the size of the hole called out in the plans was the bottom of a mixing cup (I have to wonder if this is just a coincidence).

After I cut the holes I gouged out some foam, I then filled in the void with flox to make a nice sturdy edge.


Completed headrest.


Foam routed out for flox reenforcement


map holder in action


Beverage holder?

Saturday, March 1, 2008

Chapter 7 - Seat belts and rollover - Part 1

Chapter 6 is complete, finally! This next chapter should go really fast. Pictured is my co-pilot trying out the cockpit. On the left you can see my shop assistant Bender. He is not good for much, but if I need anything bent.....

I have started to work on the roll over structure. I am awaiting a shipment of epoxy resin and I will glass the inside of the roll over parts as soon as it arrives next week.

I plan on using a gas strut for the canopy stay so I have a couple of plywood inserts in the back of the roll over as pictured. The other two small foam pieces with inserts are reinforcement for the shoulder harnes attachment bolts.